Wind farm facts

StatusOperational
County / regionDerbyshire
Turbines4
Installed capacity8 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Carsington Wind Energy Limited
Turbine manufacturernot recorded
Turbine modelnot recorded
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

→ ~20362010201520202025today123456
  1. 1Jan 2007 — Application submitted
  2. 2Jul 2007 — Refused
  3. 3Sep 2008 — Permission granted
  4. 4Sep 2008 — Granted on appeal
  5. 5May 2012 — Under construction
  6. 6Feb 2014 — Operational

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4665.

What the register tells us

The application was determined in about 20 months. Construction to first power took about 21 months. The register records a refusal in July 2007 before the scheme progressed. Permission was ultimately granted on appeal in September 2008. The scheme has been operating for about 12 years. That works out at 2 MW per turbine on average.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.