Castle Pill - Repowering

4 turbines · operational · Dyfed

Wind farm facts

StatusOperational
County / regionDyfed
Turbines4
Installed capacity3.2 MW
Turbine capacity0.8 MW
Tip heightnot recorded
Operator (or applicant)John Laing Environmental Assets Group
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2004 2005 2006 2007 2008 2009 2010 Project timeline Application submitted June 2005 Refused December 2005 Permission granted December 2005 Granted on appeal December 2005 Operational June 2009

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3313.

What the register tells us

The application was determined in about 6 months. The register records a refusal in December 2005 before the scheme progressed. Permission was ultimately granted on appeal in December 2005. The scheme has been operating for about 17 years. That works out at 0.8 MW per turbine on average.