Celcon Blocks Ltd

1 turbines · operational · Humberside

Wind farm facts

StatusOperational
County / regionHumberside
Turbines1
Installed capacity2 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Ecotricity / Next Generation
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted August 2009 Permission granted October 2012 Granted on appeal October 2012 Permission expired October 2012 Under construction April 2015 Operational April 2016 Refused April 2018

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2695.

What the register tells us

The application was determined in about 38 months. Construction to first power took about 12 months. The register records a refusal in April 2018 before the scheme progressed. Permission was ultimately granted on appeal in October 2012. A planning permission on this site expired in October 2012. The scheme has been operating for about 10 years. That works out at 2 MW per turbine on average.