Checkley Wood Farm

1 turbines · operational · Bedfordshire

Wind farm facts

StatusOperational
County / regionBedfordshire
Turbines1
Installed capacity4.1 MW
Turbine capacity4.1 MW
Tip height150 m
Operator (or applicant)AW Group
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 Project timeline Application submitted April 2016 Permission granted September 2017 Permission expired September 2022 Under construction May 2023 Operational January 2024

From application to operation, this scheme took about 8 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 6120.

What the register tells us

The application was determined in about 17 months. Construction to first power took about 8 months. A planning permission on this site expired in September 2022. The scheme has been operating for about 2 years. That works out at 4.1 MW per turbine on average.