🌬️ Onshore wind farm

Chelker Reservoir (Retention of Turbines)
North Yorkshire

Recorded in WhichWindTurbine: 4 wind turbines in operation. Point the app at one of them to see its profile in real time.

4
turbines
1.2 MW
MW total
0.3 MW
per turbine

📍 4 turbines mapped — each dot is a turbine recorded in the database. Average position: 53.95918 N · 1.92949 W.

Chelker Reservoir (Retention of Turbines)

4 turbines · operational · North Yorkshire

Wind farm facts

StatusOperational
County / regionNorth Yorkshire
Turbines4
Installed capacity1.2 MW
Turbine capacity0.3 MW
Tip heightnot recorded
Operator (or applicant)Yorkshire Water
Turbine manufacturernot recorded
Turbine modelnot recorded
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

~2026 reached20052010201520202025today123
  1. 1Jan 2001 — Application submitted
  2. 2May 2001 — Permission granted
  3. 3May 2004 — Operational

The register also records a planning permission expiry in May 2014, after commissioning: an administrative date with no effect on the operating wind farm, left off the axis.

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2747.

What the register tells us

The application was determined in about 4 months. A planning permission on this site expired in May 2014. The scheme has been operating for about 22 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 0.3 MW per turbine on average.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.