4 turbines · operational · Northamptonshire
| Status | Operational |
|---|---|
| County / region | Northamptonshire |
| Turbines | 4 |
| Installed capacity | 10 MW |
| Turbine capacity | 2.5 MW |
| Tip height | not recorded |
| Operator (or applicant) | Chelveston Renewable Energy Ltd |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 4 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3795.
The application was determined in about 27 months. Construction to first power took about 6 months. The register records a refusal in March 2011 before the scheme progressed. Permission was ultimately granted on appeal in June 2012. The scheme has been operating for about 12 years. That works out at 2.5 MW per turbine on average.