Chelveston Renewable Energy Park Wind Farm (Bedford)

4 turbines · operational · Northamptonshire

Wind farm facts

StatusOperational
County / regionNorthamptonshire
Turbines4
Installed capacity10 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Chelveston Renewable Energy Ltd
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2009 2010 2011 2012 2013 2014 2015 Project timeline Application submitted March 2010 Refused March 2011 Permission granted June 2012 Granted on appeal June 2012 Under construction August 2013 Operational February 2014

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3795.

What the register tells us

The application was determined in about 27 months. Construction to first power took about 6 months. The register records a refusal in March 2011 before the scheme progressed. Permission was ultimately granted on appeal in June 2012. The scheme has been operating for about 12 years. That works out at 2.5 MW per turbine on average.