🌬️ Onshore wind farm

Chelveston Renewable Energy Park Wind Farm (East Northamptonshire)
Northamptonshire

Recorded in WhichWindTurbine: 5 wind turbines in operation. Point the app at one of them to see its profile in real time.

5
turbines
12.5 MW
MW total
2.5 MW
per turbine

📍 5 turbines mapped — each dot is a turbine recorded in the database. Average position: 52.3085 N · 0.51948 W.

Chelveston Renewable Energy Park Wind Farm (East Northamptonshire)

5 turbines · operational · Northamptonshire

Wind farm facts

StatusOperational
County / regionNorthamptonshire
Turbines5
Installed capacity12.5 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Chelveston Renewable Energy
Turbine manufacturernot recorded
Turbine modelnot recorded
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

→ ~2036201520202025today123456
  1. 1Mar 2010 — Application submitted
  2. 2Mar 2011 — Refused
  3. 3Jun 2012 — Permission granted
  4. 4Jun 2012 — Granted on appeal
  5. 5Aug 2013 — Under construction
  6. 6Feb 2014 — Operational

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3946.

What the register tells us

The application was determined in about 27 months. Construction to first power took about 6 months. The register records a refusal in March 2011 before the scheme progressed. Permission was ultimately granted on appeal in June 2012. The scheme has been operating for about 12 years. That works out at 2.5 MW per turbine on average.

Nearby

See all wind farms in Northamptonshire.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.