Cloonty Wind Farm

4 turbines · operational · Co. Antrim

Wind farm facts

StatusOperational
County / regionCo. Antrim
Turbines4
Installed capacity12 MW
Turbine capacity3 MW
Tip heightnot recorded
Operator (or applicant)Gaelectric Developments/ CGN Europe Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted June 2009 Permission granted March 2013 Under construction October 2015 Operational August 2016 Permission expired March 2018

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4143.

What the register tells us

The application was determined in about 45 months. Construction to first power took about 10 months. A planning permission on this site expired in March 2018. The scheme has been operating for about 10 years. That works out at 3 MW per turbine on average.