Coire Na Cloiche Wind Farm

13 turbines · operational · Highland

Wind farm facts

StatusOperational
County / regionHighland
Turbines13
Installed capacity29.9 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)RockbySea
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 Project timeline Application submitted February 2012 Permission granted April 2013 Permission expired April 2016 Under construction August 2017 Operational March 2020

From application to operation, this scheme took about 8 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3846.

What the register tells us

The application was determined in about 14 months. Construction to first power took about 31 months. A planning permission on this site expired in April 2016. The scheme has been operating for about 6 years. That works out at 2.3 MW per turbine on average.