Coldham Hall

8 turbines · operational · Cambridgeshire

Wind farm facts

StatusOperational
County / regionCambridgeshire
Turbines8
Installed capacity14 MW
Turbine capacity1.75 MW
Tip heightnot recorded
Operator (or applicant)Co-op
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Project timeline Application submitted January 2002 Permission granted October 2002 Operational August 2005 Permission expired October 2015

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3479.

What the register tells us

The application was determined in about 9 months. A planning permission on this site expired in October 2015. The scheme has been operating for about 21 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 1.75 MW per turbine on average.