Corby Knowe

3 turbines · operational · Co. Antrim

Wind farm facts

StatusOperational
County / regionCo. Antrim
Turbines3
Installed capacity5 MW
Turbine capacity1.6 MW
Tip heightnot recorded
Operator (or applicant)Gaelectric Developments/ CGN Europe Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted November 2006 Permission granted January 2013 Under construction January 2016 Operational May 2017 Permission expired January 2018

From application to operation, this scheme took about 11 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4246.

What the register tells us

The application was determined in about 74 months. Construction to first power took about 16 months. A planning permission on this site expired in January 2018. The scheme has been operating for about 9 years. That works out at 1.67 MW per turbine on average.

Nearby

See all wind farms in Co. Antrim.