10 turbines · operational · Co. Antrim
| Status | Operational |
|---|---|
| County / region | Co. Antrim |
| Turbines | 10 |
| Installed capacity | 5 MW |
| Turbine capacity | 0.5 MW |
| Tip height | not recorded |
| Operator (or applicant) | B9 Energy Services Ltd/ ScottishPower Renewables |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 1 year.
The register links a second scheme on this site (REPD ref 3852, Operational): 1 turbines · 2.5 MW each · applicant Northern Ireland Renewables. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3103.
The application was determined in about 7 months. The scheme has been operating for about 32 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 0.5 MW per turbine on average.
See all wind farms in Co. Antrim.