Corriegarth

23 turbines · operational · Highland

Wind farm facts

StatusOperational
County / regionHighland
Turbines23
Installed capacity69.5 MW
Turbine capacity3 MW
Tip height120 m
Operator (or applicant)Greencoat Capital
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Project timeline Application submitted July 2007 Permission granted April 2015 Under construction May 2015 Operational September 2016

From application to operation, this scheme took about 9 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4664.

What the register tells us

The application was determined in about 93 months. Construction to first power took about 16 months. The scheme has been operating for about 10 years. That works out at 3.02 MW per turbine on average.