Corriemoillie

17 turbines · operational · Highland

Wind farm facts

StatusOperational
County / regionHighland
Turbines17
Installed capacity54.4 MW
Turbine capacity3.2 MW
Tip height125 m
Operator (or applicant)EDF Energy Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted October 2010 Permission granted March 2011 Under construction October 2015 Operational April 2017

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4120.

What the register tells us

The application was determined in about 5 months. Construction to first power took about 18 months. The scheme has been operating for about 9 years. That works out at 3.2 MW per turbine on average.