Courtstone Wind Turbine

1 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines1
Installed capacity2.3 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Private Developer
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Project timeline Application submitted September 2006 Permission granted September 2006 Operational June 2009 Permission expired September 2015

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2782.

What the register tells us

The application was determined in about 0 month. A planning permission on this site expired in September 2015. The scheme has been operating for about 17 years. That works out at 2.3 MW per turbine on average.

Nearby

See all wind farms in Grampian.