Craigannet Farm Wind Turbine

1 turbines · operational · Stirling

Wind farm facts

StatusOperational
County / regionStirling
Turbines1
Installed capacity1.5 MW
Turbine capacity1.5 MW
Tip heightnot recorded
Operator (or applicant)Clean Earth Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2014 2015 2016 2017 2018 Project timeline Application submitted April 2015 Permission granted August 2015 Under construction December 2016 Operational March 2017

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 6318.

What the register tells us

The application was determined in about 4 months. Construction to first power took about 3 months. The scheme has been operating for about 9 years. That works out at 1.5 MW per turbine on average.