Craigengelt

8 turbines · operational · Stirling

Wind farm facts

StatusOperational
County / regionStirling
Turbines8
Installed capacity20 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Scotia Wind Ltd
Turbine manufacturerNordex
Turbine modelN90

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 2011 Project timeline Application submitted December 2006 Permission granted February 2008 Under construction May 2009 Operational March 2010

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2940.

What the register tells us

The application was determined in about 14 months. Construction to first power took about 10 months. The scheme has been operating for about 16 years. That works out at 2.5 MW per turbine on average.