Craiggore windfarm

10 turbines · operational · Co. Derry / Londonderry

Wind farm facts

StatusOperational
County / regionCo. Derry / Londonderry
Turbines10
Installed capacity23.5 MW
Turbine capacity1.8 MW
Tip heightnot recorded
Operator (or applicant)Renewable Energy Systems (RES)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 Project timeline Application submitted October 2012 Permission granted March 2015 Under construction September 2019 Permission expired March 2020

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4297.

What the register tells us

The application was determined in about 29 months. A planning permission on this site expired in March 2020. That works out at 2.35 MW per turbine on average.