Crimp Wind Farm

3 turbines · operational · Cornwall

Wind farm facts

StatusOperational
County / regionCornwall
Turbines3
Installed capacity2.4 MW
Turbine capacity0.8 MW
Tip heightnot recorded
Operator (or applicant)Crimp Power Ltd (West Coast Energy)
Turbine manufacturerEnercon
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 Project timeline Application submitted December 2004 Refused April 2007 Permission granted April 2008 Granted on appeal April 2008 Under construction August 2010 Operational April 2011

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3458.

What the register tells us

The application was determined in about 40 months. Construction to first power took about 8 months. The register records a refusal in April 2007 before the scheme progressed. Permission was ultimately granted on appeal in April 2008. The scheme has been operating for about 15 years. That works out at 0.8 MW per turbine on average.