Crockagarron Ext

1 turbines · operational · Co. Tyrone

Wind farm facts

StatusOperational
County / regionCo. Tyrone
Turbines1
Installed capacity2.5 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Northern Wind Power�
Turbine manufacturerNordex
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 Project timeline Application submitted March 2009 Permission granted December 2010 Under construction April 2012 Operational June 2012

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3717.

What the register tells us

The application was determined in about 21 months. Construction to first power took about 2 months. The scheme has been operating for about 14 years. That works out at 2.5 MW per turbine on average.