Crockandun

6 turbines · operational · Co. Derry / Londonderry

Wind farm facts

StatusOperational
County / regionCo. Derry / Londonderry
Turbines6
Installed capacity15 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Brookfield Renewable Energy Group
Turbine manufacturerNordex
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted January 2010 Permission granted November 2012 Under construction January 2016 Operational March 2017 Permission expired November 2017

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4156.

What the register tells us

The application was determined in about 34 months. Construction to first power took about 14 months. A planning permission on this site expired in November 2017. The scheme has been operating for about 9 years. That works out at 2.5 MW per turbine on average.

Nearby

See all wind farms in Co. Derry / Londonderry.