Crook Hill (Calderdale MBC) 1 of 2

4 turbines · operational · Greater Manchester

Wind farm facts

StatusOperational
County / regionGreater Manchester
Turbines4
Installed capacity13.6 MW
Turbine capacity3.4 MW
Tip heightnot recorded
Operator (or applicant)Infrared Capital Partners
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Project timeline Application submitted August 2008 Permission granted October 2009 Under construction January 2015 Operational December 2015

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4354.

What the register tells us

The application was determined in about 14 months. Construction to first power took about 11 months. The scheme has been operating for about 11 years. That works out at 3.4 MW per turbine on average.