Crossdykes

10 turbines · operational · Dumfries and Galloway

Wind farm facts

StatusOperational
County / regionDumfries and Galloway
Turbines10
Installed capacity48 MW
Turbine capacity4.8 MW
Tip height177 m
Operator (or applicant)Muirhall Energy
Turbine manufacturerSiemens Gamesa
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2017 2018 2019 2020 2021 2022 Project timeline Permission expired June 2018 Application submitted November 2018 Permission granted June 2019 Under construction August 2019 Operational June 2021

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4633.

What the register tells us

The application was determined in about 7 months. Construction to first power took about 22 months. A planning permission on this site expired in June 2018. The scheme has been operating for about 5 years. That works out at 4.8 MW per turbine on average.