Cumberhead Wind Farm

12 turbines · operational · Lanarkshire

Wind farm facts

StatusOperational
County / regionLanarkshire
Turbines12
Installed capacity48 MW
Turbine capacitynot recorded
Tip heightnot recorded
Operator (or applicant)Octopus Renewables Infrastructure Trust
Turbine manufacturerNordex
Turbine modelN133

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 Project timeline Application submitted June 2015 Permission granted May 2021 Under construction October 2021 Operational September 2023

From application to operation, this scheme took about 8 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 5455.

What the register tells us

The application was determined in about 71 months. Construction to first power took about 23 months. The scheme has been operating for about 3 years. That works out at 4 MW per turbine on average.