9 turbines · operational · Leicestershire
| Status | Operational |
|---|---|
| County / region | Leicestershire |
| Turbines | 9 |
| Installed capacity | 7.2 MW |
| Turbine capacity | 0.8 MW |
| Tip height | 77 m |
| Operator (or applicant) | Ecotricity |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 6 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3764.
The application was determined in about 7 months. Construction to first power took about 13 months. A planning permission on this site expired in December 2019. The scheme has been operating for about 10 years. That works out at 0.8 MW per turbine on average.