Dalby

9 turbines · operational · Leicestershire

Wind farm facts

StatusOperational
County / regionLeicestershire
Turbines9
Installed capacity7.2 MW
Turbine capacity0.8 MW
Tip height77 m
Operator (or applicant)Ecotricity
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 Project timeline Application submitted May 2010 Permission granted December 2010 Under construction February 2015 Operational March 2016 Permission expired December 2019

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3764.

What the register tells us

The application was determined in about 7 months. Construction to first power took about 13 months. A planning permission on this site expired in December 2019. The scheme has been operating for about 10 years. That works out at 0.8 MW per turbine on average.