Dalquhandy Windfarm

10 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines10
Installed capacity42 MW
Turbine capacity4.2 MW
Tip height149.9 m
Operator (or applicant)Dalquhandy Wind Farm Limited
Turbine manufacturerNordex
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 Project timeline Application submitted February 2012 Permission granted January 2015 Permission expired January 2020 Operational January 2023

From application to operation, this scheme took about 11 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4189.

What the register tells us

The application was determined in about 35 months. A planning permission on this site expired in January 2020. The scheme has been operating for about 3 years. That works out at 4.2 MW per turbine on average.