Dalswinton

15 turbines · operational · Dumfries and Galloway

Wind farm facts

StatusOperational
County / regionDumfries and Galloway
Turbines15
Installed capacity30 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Airtricity Scotland
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 Project timeline Application submitted October 2003 Permission granted January 2005 Under construction April 2007 Operational March 2008 Permission expired January 2013

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4520.

What the register tells us

The application was determined in about 15 months. Construction to first power took about 11 months. A planning permission on this site expired in January 2013. The scheme has been operating for about 18 years. That works out at 2 MW per turbine on average.