Darracott Moor

3 turbines · operational · Devon

Wind farm facts

StatusOperational
County / regionDevon
Turbines3
Installed capacity2.6 MW
Turbine capacity0.85 MW
Tip heightnot recorded
Operator (or applicant)Gresham House
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2001 2003 2005 2007 2009 2011 2013 2015 2017 2019 Project timeline Application submitted July 2002 Refused February 2003 Permission granted May 2004 Granted on appeal May 2004 Under construction October 2006 Operational May 2011 Permission expired May 2018

From application to operation, this scheme took about 9 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3450.

What the register tells us

The application was determined in about 22 months. Construction to first power took about 55 months. The register records a refusal in February 2003 before the scheme progressed. Permission was ultimately granted on appeal in May 2004. A planning permission on this site expired in May 2018. The scheme has been operating for about 15 years. That works out at 0.87 MW per turbine on average.