3 turbines · operational · Devon
| Status | Operational |
|---|---|
| County / region | Devon |
| Turbines | 3 |
| Installed capacity | 2.6 MW |
| Turbine capacity | 0.85 MW |
| Tip height | not recorded |
| Operator (or applicant) | Gresham House |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 9 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3450.
The application was determined in about 22 months. Construction to first power took about 55 months. The register records a refusal in February 2003 before the scheme progressed. Permission was ultimately granted on appeal in May 2004. A planning permission on this site expired in May 2018. The scheme has been operating for about 15 years. That works out at 0.87 MW per turbine on average.
See all wind farms in Devon.