Den Brook

9 turbines · operational · Devon

Wind farm facts

StatusOperational
County / regionDevon
Turbines9
Installed capacity18 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Aviva
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Project timeline Application submitted November 2005 Refused March 2006 Permission granted March 2007 Permission expired March 2010 Under construction August 2015 Operational November 2016

From application to operation, this scheme took about 11 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4266.

What the register tells us

The application was determined in about 16 months. Construction to first power took about 15 months. The register records a refusal in March 2006 before the scheme progressed. A planning permission on this site expired in March 2010. The scheme has been operating for about 10 years. That works out at 2 MW per turbine on average.