Derby Sewage Treatment Works

2 turbines · operational · Derbyshire

Wind farm facts

StatusOperational
County / regionDerbyshire
Turbines2
Installed capacity5 MW
Turbine capacity3.4 MW
Tip heightnot recorded
Operator (or applicant)Severn Trent Water
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2009 2010 2011 2012 2013 2014 2015 Project timeline Application submitted October 2010 Permission granted October 2012 Under construction May 2013 Operational May 2014

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4068.

What the register tells us

The application was determined in about 24 months. Construction to first power took about 12 months. The scheme has been operating for about 12 years. That works out at 2.5 MW per turbine on average.