Deuchries Windfarm (extension) (Bradley 2)

2 turbines · operational · Aberdeenshire

Wind farm facts

StatusOperational
County / regionAberdeenshire
Turbines2
Installed capacity4.7 MW
Turbine capacity2.35 MW
Tip height119 m
Operator (or applicant)Blackfinch Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2018 2019 2020 2021 2022 2023 2024 2025 Project timeline Application submitted January 2019 Permission granted August 2019 Permission expired October 2022 Operational August 2024

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 7304.

What the register tells us

The application was determined in about 7 months. A planning permission on this site expired in October 2022. The scheme has been operating for about 2 years. That works out at 2.35 MW per turbine on average.