Dewlay Cheese Wind Turbine

1 turbines · operational · Lancashire

Wind farm facts

StatusOperational
County / regionLancashire
Turbines1
Installed capacity2 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Dewlay Cheese Company
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2007 2008 2009 2010 2011 Project timeline Application submitted June 2008 Permission granted September 2008 Under construction October 2010 Operational November 2010

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3078.

What the register tells us

The application was determined in about 3 months. Construction to first power took about 1 month. The scheme has been operating for about 16 years. That works out at 2 MW per turbine on average.

Nearby

See all wind farms in Lancashire.