2 turbines · operational · Grampian
| Status | Operational |
|---|---|
| County / region | Grampian |
| Turbines | 2 |
| Installed capacity | 4.6 MW |
| Turbine capacity | 2.3 MW |
| Tip height | not recorded |
| Operator (or applicant) | Macphie Of Glenbervie Ltd |
| Turbine manufacturer | Enercon |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 5 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3398.
The application was determined in about 47 months. Construction to first power took about 10 months. The scheme has been operating for about 12 years. That works out at 2.3 MW per turbine on average.
See all wind farms in Grampian.