Dunmore

7 turbines · operational · Co. Derry / Londonderry

Wind farm facts

StatusOperational
County / regionCo. Derry / Londonderry
Turbines7
Installed capacity21 MW
Turbine capacity3 MW
Tip heightnot recorded
Operator (or applicant)TCI Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 Original scheme Application submitted December 2007 Refused April 2009 Permission granted October 2010 Granted on appeal October 2010 Permission expired October 2012 Operational April 2013 Later scheme Application submitted November 2013 Refused April 2017 Permission granted June 2018 Granted on appeal June 2018 Permission expired June 2023

From application to operation, this scheme took about 6 years.

The register links a second scheme on this site (REPD ref 4301, Awaiting Construction): 8 turbines · 3 MW each · applicant TCI Renewables. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3969.

What the register tells us

The application was determined in about 34 months. The register records a refusal in April 2009 before the scheme progressed. Permission was ultimately granted on appeal in October 2010. A planning permission on this site expired in October 2012. The scheme has been operating for about 13 years. That works out at 3 MW per turbine on average.

Nearby

See all wind farms in Co. Derry / Londonderry.