Dunsland Cross Wind Farm

3 turbines · operational · Devon

Wind farm facts

StatusOperational
County / regionDevon
Turbines3
Installed capacity7.5 MW
Turbine capacity3 MW
Tip heightnot recorded
Operator (or applicant)Temporis Capital
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted January 2012 Refused January 2013 Permission granted January 2013 Granted on appeal January 2013 Permission expired January 2013 Under construction January 2016 Operational March 2017

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4227.

What the register tells us

The application was determined in about 12 months. Construction to first power took about 14 months. The register records a refusal in January 2013 before the scheme progressed. Permission was ultimately granted on appeal in January 2013. A planning permission on this site expired in January 2013. The scheme has been operating for about 9 years. That works out at 2.5 MW per turbine on average.

Nearby

See all wind farms in Devon.