Recorded in WhichWindTurbine: 14 wind turbines in operation. Point the app at one of them to see its profile in real time.
📍 14 turbines mapped — each dot is a turbine recorded in the database. Average position: 56.07145 N · 4.10425 W.
14 turbines · operational · Stirling
| Status | Operational |
|---|---|
| County / region | Stirling |
| Turbines | 14 |
| Installed capacity | 37.5 MW |
| Turbine capacity | 2.5 MW |
| Tip height | not recorded |
| Operator (or applicant) | Falck Renewables |
| Turbine manufacturer | Nordex |
| Turbine model | N80/2500 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
The register also records a planning permission expiry in Jul 2017, after construction had started: an administrative date with no effect on the wind farm, left off the axis.
DevelopmentConstructionOperationAhead (repowering horizon at 22 years)
From application to operation, this scheme took about 4 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3201.
The application was determined in about 8 months. Construction to first power took about 7 months. A planning permission on this site expired in July 2017. The scheme has been operating for about 19 years. That works out at 2.68 MW per turbine on average.
| Data | Source | Extract |
|---|---|---|
| Site, capacity, status, planning milestones | Renewable Energy Planning Database (DESNZ, Open Government Licence v3) | Q2 2026, published 03/08/2026 |
| Turbine positions | OpenStreetMap contributors (ODbL) | 19/08/2026 |
| Manufacturer and model | OpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong. | 19/08/2026 |
Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.