9 turbines · operational · Stirling
| Status | Operational |
|---|---|
| County / region | Stirling |
| Turbines | 9 |
| Installed capacity | 22.5 MW |
| Turbine capacity | 2.5 MW |
| Tip height | not recorded |
| Operator (or applicant) | Falck Renewables |
| Turbine manufacturer | Nordex |
| Turbine model | N80/2500 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 8 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4247.
The application was determined in about 26 months. Construction to first power took about 23 months. A planning permission on this site expired in April 2018. The scheme has been operating for about 10 years. That works out at 2.5 MW per turbine on average.