14 turbines · operational · Stirling
| Status | Operational |
|---|---|
| County / region | Stirling |
| Turbines | 14 |
| Installed capacity | 37.5 MW |
| Turbine capacity | 2.5 MW |
| Tip height | not recorded |
| Operator (or applicant) | Falck Renewables |
| Turbine manufacturer | Nordex |
| Turbine model | N80/2500 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 4 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3201.
The application was determined in about 8 months. Construction to first power took about 7 months. A planning permission on this site expired in July 2017. The scheme has been operating for about 19 years. That works out at 2.68 MW per turbine on average.