Easter Tolmauds

2 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines2
Installed capacity1.6 MW
Turbine capacity0.8 MW
Tip heightnot recorded
Operator (or applicant)Frank A Smart & Son Ltd
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted May 2014 Refused August 2014 Permission granted May 2015 Granted on appeal May 2015 Under construction February 2016 Operational October 2016 Permission expired May 2018

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4133.

What the register tells us

The application was determined in about 12 months. Construction to first power took about 8 months. The register records a refusal in August 2014 before the scheme progressed. Permission was ultimately granted on appeal in May 2015. A planning permission on this site expired in May 2018. The scheme has been operating for about 10 years. That works out at 0.8 MW per turbine on average.

Nearby

See all wind farms in Grampian.