🌬️ Onshore wind farm

Easter Tulloch Wind Farm (Tullo Extension)
Grampian

Recorded in WhichWindTurbine: 10 wind turbines in operation. Point the app at one of them to see its profile in real time.

10
turbines
25 MW
MW total
2.5 MW
per turbine

📍 10 turbines mapped — each dot is a turbine recorded in the database. Average position: 56.83928 N · 2.40052 W.

Easter Tulloch Wind Farm (Tullo Extension)

10 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines10
Installed capacity25 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)N R Gammie Partnership
Turbine manufacturerNordex
Turbine modelnot recorded
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

→ ~2036201520202025today1234
  1. 1Aug 2011 — Application submitted
  2. 2Sep 2012 — Permission granted
  3. 3May 2013 — Under construction
  4. 4Jun 2014 — Operational

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4365.

What the register tells us

The application was determined in about 13 months. Construction to first power took about 13 months. The scheme has been operating for about 12 years. That works out at 2.5 MW per turbine on average.

Nearby

See all wind farms in Grampian.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.