Edinbane Wind Farm

18 turbines · operational · Highland

Wind farm facts

StatusOperational
County / regionHighland
Turbines18
Installed capacity41.4 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Vattenfall
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 Project timeline Application submitted February 2002 Permission granted May 2007 Under construction August 2008 Operational June 2010

From application to operation, this scheme took about 8 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4674.

What the register tells us

The application was determined in about 63 months. Construction to first power took about 22 months. The scheme has been operating for about 16 years. That works out at 2.3 MW per turbine on average.