Eglish Mountain

6 turbines · operational · Co. Tyrone

Wind farm facts

StatusOperational
County / regionCo. Tyrone
Turbines6
Installed capacity13.8 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)ESB (Northern Wind Power)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted February 2005 Permission granted July 2013 Under construction October 2015 Operational January 2017 Permission expired July 2018

From application to operation, this scheme took about 12 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4264.

What the register tells us

The application was determined in about 101 months. Construction to first power took about 15 months. A planning permission on this site expired in July 2018. The scheme has been operating for about 9 years. That works out at 2.3 MW per turbine on average.

Nearby

See all wind farms in Co. Tyrone.