Energy Works Hull - Wind Turbine

1 turbines · operational · Humberside

Wind farm facts

StatusOperational
County / regionHumberside
Turbines1
Installed capacity3 MW
Turbine capacity3 MW
Tip heightnot recorded
Operator (or applicant)Spencer Group
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted June 2011 Permission granted October 2011 Permission expired October 2013 Under construction November 2015 Operational March 2018

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3893.

What the register tells us

The application was determined in about 4 months. Construction to first power took about 28 months. A planning permission on this site expired in October 2013. The scheme has been operating for about 8 years. That works out at 3 MW per turbine on average.