🌬️ Onshore wind farm

Energy Works Hull - Wind Turbine
Humberside

Recorded in WhichWindTurbine: 1 wind turbine in operation. Point the app at one of them to see its profile in real time.

1
turbines
3 MW
MW total
3 MW
per turbine

📍 1 turbine mapped — each dot is a turbine recorded in the database. Average position: 53.77338 N · 0.34339 W.

Energy Works Hull - Wind Turbine

1 turbines · operational · Humberside

Wind farm facts

StatusOperational
County / regionHumberside
Turbines1
Installed capacity3 MW
Turbine capacity3 MW
Tip heightnot recorded
Operator (or applicant)Spencer Group
Turbine manufacturernot recorded
Turbine modelnot recorded
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

→ ~2040201520202025today12345
  1. 1Jun 2011 — Application submitted
  2. 2Oct 2011 — Permission granted
  3. 3Oct 2013 — Permission expired
  4. 4Nov 2015 — Under construction
  5. 5Mar 2018 — Operational

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3893.

What the register tells us

The application was determined in about 4 months. Construction to first power took about 28 months. A planning permission on this site expired in October 2013. The scheme has been operating for about 8 years. That works out at 3 MW per turbine on average.

Nearby

See all wind farms in Humberside.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.