16 turbines · operational · Dumfries and Galloway
| Status | Operational |
|---|---|
| County / region | Dumfries and Galloway |
| Turbines | 16 |
| Installed capacity | 36.8 MW |
| Turbine capacity | 2.3 MW |
| Tip height | not recorded |
| Operator (or applicant) | Scottish Power Renewables |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 13 years.
The register links a second scheme on this site (REPD ref 4015, Operational): 6 turbines · 2.3 MW each · applicant Scottish Power Renewables. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3627.
The application was determined in about 122 months. Construction to first power took about 10 months. The scheme has been operating for about 9 years. That works out at 2.3 MW per turbine on average.
See all wind farms in Dumfries and Galloway.