20 turbines · operational · Highland
| Status | Operational |
|---|---|
| County / region | Highland |
| Turbines | 20 |
| Installed capacity | 43 MW |
| Turbine capacity | 2.15 MW |
| Tip height | not recorded |
| Operator (or applicant) | Scottish and Southern Energy (SSE) |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 5 years.
The register links a second scheme on this site (REPD ref 3883, Application Withdrawn): 12 turbines · 3 MW each · applicant Scottish and Southern Energy (SSE). Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4675.
The application was determined in about 32 months. Construction to first power took about 16 months. A planning permission on this site expired in January 2000. The scheme has been operating for about 16 years. That works out at 2.15 MW per turbine on average.
See all wind farms in Highland.