Fanny House Farm/Heysham Moss

1 turbines · operational · Lancashire

Wind farm facts

StatusOperational
County / regionLancashire
Turbines1
Installed capacity1.5 MW
Turbine capacity1.5 MW
Tip height110 m
Operator (or applicant)Blue Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted January 2011 Permission granted October 2012 Under construction January 2014 Operational February 2015 Permission expired October 2017

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3792.

What the register tells us

The application was determined in about 21 months. Construction to first power took about 13 months. A planning permission on this site expired in October 2017. The scheme has been operating for about 11 years. That works out at 1.5 MW per turbine on average.