Fen Farm

20 turbines · operational · Lincolnshire

Wind farm facts

StatusOperational
County / regionLincolnshire
Turbines20
Installed capacity16 MW
Turbine capacity0.8 MW
Tip heightnot recorded
Operator (or applicant)Ecotricity
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 Project timeline Application submitted July 2003 Permission granted November 2004 Under construction February 2007 Operational April 2008 Permission expired November 2014

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3449.

What the register tells us

The application was determined in about 16 months. Construction to first power took about 14 months. A planning permission on this site expired in November 2014. The scheme has been operating for about 18 years. That works out at 0.8 MW per turbine on average.

Nearby

See all wind farms in Lincolnshire.