4 turbines · operational · Mid Glamorgan
| Status | Operational |
|---|---|
| County / region | Mid Glamorgan |
| Turbines | 4 |
| Installed capacity | 10 MW |
| Turbine capacity | 2.5 MW |
| Tip height | not recorded |
| Operator (or applicant) | Pennant Walters |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 7 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3956.
The application was determined in about 57 months. Construction to first power took about 19 months. A planning permission on this site expired in May 2011. The scheme has been operating for about 13 years. That works out at 2.5 MW per turbine on average.
See all wind farms in Mid Glamorgan.