Ford Motor Company Ltd (Extension)

1 turbines · operational · London

Wind farm facts

StatusOperational
County / regionLondon
Turbines1
Installed capacity2 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Unknown
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 Project timeline Application submitted April 2009 Permission granted July 2009 Under construction January 2010 Operational August 2011 Permission expired July 2012

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2683.

What the register tells us

The application was determined in about 3 months. Construction to first power took about 19 months. A planning permission on this site expired in July 2012. The scheme has been operating for about 15 years. That works out at 2 MW per turbine on average.